Community Hub

MVHS Community Hub

A new home for the community, now under construction

Progress update · as of 29 October 2026

Nearing completion

Work on the Community Hub is slowly coming to the critical completion phase. We anticipate a soft opening in December 2026, with a formal opening in the new year.

Completed

  • Concrete flooring throughout: the basement, ground floor, first floor, retail area and conference room area
  • The roof over the first floor
  • The rough-in for the electrician and plumber
  • Concrete poured for the block walls
  • The heating and air-conditioning units installed
  • The steelwork for the canopy in front of the shops
  • The steelwork for the roof over the conference room area
  • The frames for the stud walls, largely erected

Work on the block walls has progressed steadily and is continuing.

Target budget
$5.2M ex GST
Raised so far
$3.7M including $3.5M in government grants
Soft opening
December 2026
Formal opening
Early 2027

Still to come

Expected to be finished in the next week:

  • The brickwork on the facade
  • The roofing over the conference area
  • Rendering along Forest Road and Conyers Street
  • The stud walls

Expected by the end of November 2026:

  • Installing the lifts
  • Laying the artificial timber flooring
  • Final touch-ups
Support the Hub
The building

What's inside

Mezzanine floor
Conference room and board room
First floor
The Hub
Ground floor
Car park, retail shops and the entry to the Hub
Basement
Car park

To use the Hub once it opens, please contact Dr Srinivasan through the temple office on 0404 099 444.

Artist's impression of the finished Hub: brick shopfronts under a deep dark canopy, with a glass-walled floor and balcony above
Artist's impression only.
October 2026

The works in pictures

The ground floor under its finished roof, with stud wall frames, block walls and scaffoldingSteel stud wall frames standing beneath the insulated roofAir-conditioning units and wiring hung beneath the insulated roofThe roof steelwork and cable trays, with trees beyond the open frontA ceiling air-conditioning cassette installed above a block wall and scaffolding